Stricture
- Foundation-DR Masonry (60cmx60cm),RR basement(45cmx30cm)Plinth beam (20cmx15cm)
- Plinth filling using available soil
- Masonry work using good quality cement concrete bricks
- concrete work using 20mm and 40mm crushed aggregates of M20 Mix for RCC and M7.5 mix of PCC
- Damp Proof Course on Plinth beam
- Anti-termite treatment will be provided after plinth-level backfilling
- Cement:Ultratech/ACC(For concrete)/Ramco/Shankar/Equivalent
- Steel:Kairali TMT
Electrical
- Brand :Wires:RR Cable/Equivalent
- Boxes, Switches and sockets:L&T entice
- Layout as per the standard including provisions for AC (all bedrooms)and geyser(all toilets)
Plumbing and sanitary
- Plumbing:pipes and fittings of Star/Equivalent
- Sanitary and CP Fittings up to RS 20000/Toilet of Cera /Equivalent brand
- 1000L 3-layer PVC water tank
- 2000L readymade ferrocement septic tank
Doors & Windows
- Main door:Steel door (up to RS 30000/piece)Brand:Hawaii/Equivalent
- External Door:Steel door(upto RS 18000/Piece)
- Internal door:FRP door (up to Rs11000/piece)
- Toilet door:FRP door (up to 7000/piece)
- Windows:Steel windows/upvc white profile sliding windows with grills
- MS Handrail for staircase,balcony(UPTO 15FT)(rate upto 800 Rs/Feet)
Flooring
- Flooring using Vitrified tiles, Laid using cement:Sand mortar with joint filler
- Ceramic /Vitrified toilet floor tiles with Epoxy filler
- ceramic /vitrified toilet wall tiles with epoxy filler up to 7 ft in height
- Material cost up to Rs 60/sqft for main flooring and Rs 60/sqft for toilet
- Toilet floor and wall (up to 45 cm)waterproofing
Wall finishes
- Internal painting coat putty in living, dining room and master bedroom,1 coat primer and 2 coat emulsion.Brand:Asian Apcolite premium emulsion/Equivalent
- External painting coat primer and 2 coat emulsionBrand:Asian Apex emulsion/equivalent front Elevation:2 coat putty
Kitchen and dining area
- Granite kitchen countertop to Rs 200/Sq ft *Single bowl sink with drainboard sink faucet
- Dado tiles in kitchen upto Rs 60/Sqft(2’height)
Wall-hung wash basin in dining area with CP fittings of Cera/Equivalent with towel rod, mirror and soap dish
Terms & conditions
- Rubble foundation is considered up to a depth of 60cm
- Any change in depth shall be charged accordingly on actual upon the site condition
- The package is applicable only for a minimum built-up area of 1500 Sqft or above
- Tree cutting/site levelling are excluded from this package
- The site is considered to be at road level in this package, and the plinth level is to be 45cm high from ground level.
- Any changes in this plot filling Shall be charged accordingly
- All the works shall be carried out as per the drawings.
- Any changes in the drawing as per the client’s interest shall be charged accordingly
- Water and electricity for the site shall be provided by the client.
- Rock cutting/Blasting /Compressor work is not included in this quote
- Floor hei is considered” from the floor level to the top of the slab
- Any changes in this shall be claimed accordingly
- A sloped roof, Rain water storage, Sump, and Percolation pit are excluded from this package
- Any municipal permissions, demolitions/Dismantling of existing structures, borewells, Motors, Water connection, Road cutting, and Sewage work shall be borne by the client.
- Base rate of steel -68/Kg
- Cement-390/Bag in the package
- The foundation will be finalized only after the soil test.
- Any item not mentioned in the package is additional